Screened is a word every developer uses. It usually means nothing, because the criteria behind it are never stated. Here is what it means when we use it, the criteria a site has to pass, and how screened differs from qualified and optioned. These are our working definitions. No named source defines screened, qualified, optioned, and secured as a standard four-stage set, so do not read these as industry definitions. They are ours, and we publish them so you can hold us to them.
Power is the dominant filter. That is true across the industry: CBRE’s H1 2026 report says power availability and infrastructure delivery timelines remain the most decisive factors in site selection. The checks are available load in MW, utility reserve margin, proximity to 345 kV, 230 kV, or 138 kV transmission, interconnection queue position, and time to energize. Time to energize ranges from 18 months in favorable markets to 5+ years in congested ones. Power delivery timelines across core markets have extended from 3± years to 5± years in most cases, according to a CyrusOne paper published in June 2024 and updated in January 2026. Securing a firm power commitment can take years, making it the longest lead-time item in data center development. The process begins with a load letter prepared by the project electrical engineer, detailing projected load including ramp-up and full build-out, and the utility then initiates a capacity study of transmission lines, substations, and local distribution networks. A site that cannot show a credible power path by a target date does not pass our screen, however good the land looks. A nearby substation alone does not establish that a site can receive the required MW by the required date. Powered land means land supported by a documented, site-specific path to electric service, including capacity, timing, conditions, and cost. We do not claim a signed will-serve letter that does not exist. Where the status is a utility conversation, we say so.
Fiber is the second filter, and diversity is the test. The checks are proximity to diverse routes and carrier-neutral access points, dark fiber, distance to internet exchange points, latency, and the number and diversity of providers. Most data centers need at least two physically diverse routes, and diversity means separate physical paths, not two carriers sharing one conduit or bridge crossing, so providers should be asked for route maps rather than relying on carrier counts. Confirming fiber route availability with at least two diverse paths is a minimum diligence item before capital commitment. The goal is access to multiple, geographically diverse fiber routes from different carriers, and the design must provide separate points of entry into the building. The primary fiber risks are lack of diversity and a single point of failure, and if all routes enter from the same direction or share a single conduit, one construction accident could sever all connectivity. A site with one carrier and one entry point does not pass our screen.
Land, access, flood, permitting, and cooling are the remaining gates in our process. The land checks are parcel size and contiguity, zoning, wetlands and flood zone designation, and whether the developer can secure an option, LOI, or purchase contract. In our process, a site must pass all of these gates to be screened. That is our own rule, not an industry standard. A site that fails one is not screened. It is rejected, and we say so.
Here is how we use the words, from first look to signed control. Identified means a parcel or an existing facility we have found that looks plausible on desktop review: location, acreage, a nearby substation, nearby fiber. No contact with the utility or landowner yet. Screened means it passed the desktop criteria above: a credible power path, fiber routes present, outside the floodplain, road access, zoning plausible. Several hundred sites have passed this screen: each was identified, then screened on those criteria. The criteria in this post are the definition behind that count. Qualified means it passed a deeper check: a utility conversation or a load letter submitted, fiber route maps confirmed, land control achievable. Optioned means it is under a signed option or letter of intent, with diligence periods covering utility studies and zoning, and paid extensions if those run long.
Power comes first in the screen. Aligned Data Centers describes a power-first philosophy, with strategic land acquisition and early enablement. The same CyrusOne paper states that for AI deployments, site selection prioritizes power availability, and a power-first strategy drives its approach, though proximity to population centers remains necessary for labor, maintenance, and supply networks. Power is the longest lead item and the one that most often kills a site. The criteria in this post are the screen. Several hundred sites have passed it so far. We are a global provider, and this screen is the same one we apply everywhere. The next step for any site is qualification, then an option, then a build. That is the pipeline, and that is how we will report it: identified and screened, qualified, optioned, and built, each with its own number, each defined here.
Sources
- CBRE, North America Data Center Trends H1 2026 (August 27, 2026): https://www.cbre.com/insights/books/north-america-data-center-trends-h1-2026
- Build Inc, Data Center Site Selection: The Complete Developer’s Guide: https://build.inc/insights/data-center-site-selection
- BlackForge Data Centers, Data Center Site Selection Criteria: Full Checklist: https://www.blackforgedatacenters.com/guides/data-center-site-selection-criteria
- BlackForge Data Centers, Data Center Site Selection Timeline: https://www.blackforgedatacenters.com/guides/data-center-site-selection-timeline
- RSP Engineers, Mastering the Grid: A Civil Engineer’s Guide to Data Center Utility Coordination: https://rspengineers.com/civil-engineering-blog/data-center-utility-coordination-1
- Volterra Advisors, Powered Land vs. Near Substation (undated page, viewed November 2026): https://www.volterraadvisors.com/guides/powered-land-vs-near-substation/
- CyrusOne, Navigating AI’s Impact on Data Center Infrastructure (June 2024, updated January 2026): https://www.cyrusone.com/hubfs/Website%20Documents%202025/Navigating%20AIs%20Impact%20on%20Data%20Center%20Infrastructure.pdf?hsLang=en
- Aligned Data Centers, Gigascale Campuses (undated page, viewed November 2026): https://aligneddc.com/gigascale-campuses/
- Flexential, Carrier-Neutral Data Center (undated page, viewed November 2026): https://www.flexential.com/resources/blog/carrier-neutral-data-center